Avalon Road Agricultural Enclave Public Hearing

Share Avalon Road Agricultural Enclave Public Hearing on Facebook Share Avalon Road Agricultural Enclave Public Hearing on X (formerly Twitter) Share Avalon Road Agricultural Enclave Public Hearing on Linkedin Email Avalon Road Agricultural Enclave Public Hearing link

PUBLIC HEARING UPDATE - November 10, 2026

At the November 10, 2026, Board of County Commissioners (BCC) Public Hearing, the Board voted to deny the request.


Orange County has received an application involving a property on Avalon Road in District 1. The property is located at 5477 Avalon Road; generally, north of McKinney Road, east of Alps Street within the Lake Avalon Rural Settlement. The applicant has asked the Orange County Board of County Commissioners to certify the property as an Agricultural Enclave under Florida law (known as Senate Bill 686).

What is an Agricultural Enclave?

An Agricultural Enclave is a special designation created by Florida law for certain undeveloped agricultural land that meets specific requirements related to its location, ownership, agricultural use, surrounding development, availability of public services, and acreage.

Certification would not approve a specific subdivision, site plan, or construction project. However, if the property is certified, the owner may subsequently submit applications for residential development in accordance with the process established by Florida law. Any such applications would be subject to additional reviews and approvals required by state law and the Orange County Code.

Why is Orange County processing this request?

Florida law allows a property owner to apply for Agricultural Enclave certification and requires the County to:

  • Review the application and prepare a written report evaluating whether it satisfies the statutory criteria;
  • Conduct a public hearing before the Board of County Commissioners to consider the application; and
  • Approve or deny the requested certification within the timeframes established by state law.

If the Board does not approve or deny the application within 90 days after receiving the application, Florida law requires the parcels to be certified as an Agricultural Enclave. Accordingly, Orange County is required to process the application and conduct the public hearing in accordance with the statutory procedures. The County did not initiate this request.

Public Hearing

At the hearing, the Board will consider the application, the County’s written report, information presented by the applicant, and public comments before determining whether the application satisfies the statutory requirements for Agricultural Enclave certification.

The hearing is limited to determining whether the property qualifies for Agricultural Enclave certification under Florida law.

Residents and other interested persons may attend the hearing and provide comments in accordance with the Board’s public-comment procedures.

Development Program

There is no development program at this time. If approved, Agricultural Enclave certification would allow the property owner to later submit plans for single-family residential development at a density equivalent to one or more adjacent properties or an adjacent development, as provided by Florida law.

Certification alone would not approve a specific subdivision or authorize immediate construction, but state law would require the proposed residential use to be treated as allowed even if it differs from the property’s current Future Land Use designation or zoning. Detailed development plans, engineering reviews, and applicable permits would still be required before development could occur. Orange County staff is not in a position to provide analysis or information on a potential development program due to ongoing review of the Florida law.

If you have any comments or questions, please email Jason Sorensen at jason.sorensen@ocfl.net.

PUBLIC HEARING UPDATE - November 10, 2026

At the November 10, 2026, Board of County Commissioners (BCC) Public Hearing, the Board voted to deny the request.


Orange County has received an application involving a property on Avalon Road in District 1. The property is located at 5477 Avalon Road; generally, north of McKinney Road, east of Alps Street within the Lake Avalon Rural Settlement. The applicant has asked the Orange County Board of County Commissioners to certify the property as an Agricultural Enclave under Florida law (known as Senate Bill 686).

What is an Agricultural Enclave?

An Agricultural Enclave is a special designation created by Florida law for certain undeveloped agricultural land that meets specific requirements related to its location, ownership, agricultural use, surrounding development, availability of public services, and acreage.

Certification would not approve a specific subdivision, site plan, or construction project. However, if the property is certified, the owner may subsequently submit applications for residential development in accordance with the process established by Florida law. Any such applications would be subject to additional reviews and approvals required by state law and the Orange County Code.

Why is Orange County processing this request?

Florida law allows a property owner to apply for Agricultural Enclave certification and requires the County to:

  • Review the application and prepare a written report evaluating whether it satisfies the statutory criteria;
  • Conduct a public hearing before the Board of County Commissioners to consider the application; and
  • Approve or deny the requested certification within the timeframes established by state law.

If the Board does not approve or deny the application within 90 days after receiving the application, Florida law requires the parcels to be certified as an Agricultural Enclave. Accordingly, Orange County is required to process the application and conduct the public hearing in accordance with the statutory procedures. The County did not initiate this request.

Public Hearing

At the hearing, the Board will consider the application, the County’s written report, information presented by the applicant, and public comments before determining whether the application satisfies the statutory requirements for Agricultural Enclave certification.

The hearing is limited to determining whether the property qualifies for Agricultural Enclave certification under Florida law.

Residents and other interested persons may attend the hearing and provide comments in accordance with the Board’s public-comment procedures.

Development Program

There is no development program at this time. If approved, Agricultural Enclave certification would allow the property owner to later submit plans for single-family residential development at a density equivalent to one or more adjacent properties or an adjacent development, as provided by Florida law.

Certification alone would not approve a specific subdivision or authorize immediate construction, but state law would require the proposed residential use to be treated as allowed even if it differs from the property’s current Future Land Use designation or zoning. Detailed development plans, engineering reviews, and applicable permits would still be required before development could occur. Orange County staff is not in a position to provide analysis or information on a potential development program due to ongoing review of the Florida law.

If you have any comments or questions, please email Jason Sorensen at jason.sorensen@ocfl.net.

Have a question?

Leave your question here and we will provide a response.

Email
loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
  • Share Gopher Tortoises are a protected endangered species and many have been seen nesting in this specific rural settlement in which this parcel in question is located. Has a study been conducted to identify and locate the burrows on this property and a permit filed and approved for construction activities of this magnitude to be happening around these habitats? What is the plan for these animals? If relocating them is the plan - where are we putting them where they won’t be bothered again when development continues to move further inward and encroach even further into the rural designated areas? These and other native animals keep being a forethought when they need to be a focus before we completely destroy the whole species. They need to be taken into consideration while these decisions are being discussed. on Facebook Share Gopher Tortoises are a protected endangered species and many have been seen nesting in this specific rural settlement in which this parcel in question is located. Has a study been conducted to identify and locate the burrows on this property and a permit filed and approved for construction activities of this magnitude to be happening around these habitats? What is the plan for these animals? If relocating them is the plan - where are we putting them where they won’t be bothered again when development continues to move further inward and encroach even further into the rural designated areas? These and other native animals keep being a forethought when they need to be a focus before we completely destroy the whole species. They need to be taken into consideration while these decisions are being discussed. on X (formerly Twitter) Share Gopher Tortoises are a protected endangered species and many have been seen nesting in this specific rural settlement in which this parcel in question is located. Has a study been conducted to identify and locate the burrows on this property and a permit filed and approved for construction activities of this magnitude to be happening around these habitats? What is the plan for these animals? If relocating them is the plan - where are we putting them where they won’t be bothered again when development continues to move further inward and encroach even further into the rural designated areas? These and other native animals keep being a forethought when they need to be a focus before we completely destroy the whole species. They need to be taken into consideration while these decisions are being discussed. on Linkedin Email Gopher Tortoises are a protected endangered species and many have been seen nesting in this specific rural settlement in which this parcel in question is located. Has a study been conducted to identify and locate the burrows on this property and a permit filed and approved for construction activities of this magnitude to be happening around these habitats? What is the plan for these animals? If relocating them is the plan - where are we putting them where they won’t be bothered again when development continues to move further inward and encroach even further into the rural designated areas? These and other native animals keep being a forethought when they need to be a focus before we completely destroy the whole species. They need to be taken into consideration while these decisions are being discussed. link

    Gopher Tortoises are a protected endangered species and many have been seen nesting in this specific rural settlement in which this parcel in question is located. Has a study been conducted to identify and locate the burrows on this property and a permit filed and approved for construction activities of this magnitude to be happening around these habitats? What is the plan for these animals? If relocating them is the plan - where are we putting them where they won’t be bothered again when development continues to move further inward and encroach even further into the rural designated areas? These and other native animals keep being a forethought when they need to be a focus before we completely destroy the whole species. They need to be taken into consideration while these decisions are being discussed.

    AJ asked 13 days ago

    Thank you for your question. This application is for an agricultural enclave which is a special designation created by Florida law for certain undeveloped agricultural land that meets specific criteria related to its location, ownership, agricultural use, surrounding development, availability of public services, and acreage. The criteria laid out by state law for this application does not include wildlife studies at this time. If approved, the applicant would have to follow all state and local policies relating to wildlife permitting. The Board of County Commissioners denied this application during the November 10, 2026, public hearing on the basis that this application did not meet the certification criteria.

  • Share When will Avalon Rd be widen to help traffic flow. All we do is allow new subdivision and then we wait many years to improve the roads. I believe it's just about money and taxes. I have many more questions, but I will wait. on Facebook Share When will Avalon Rd be widen to help traffic flow. All we do is allow new subdivision and then we wait many years to improve the roads. I believe it's just about money and taxes. I have many more questions, but I will wait. on X (formerly Twitter) Share When will Avalon Rd be widen to help traffic flow. All we do is allow new subdivision and then we wait many years to improve the roads. I believe it's just about money and taxes. I have many more questions, but I will wait. on Linkedin Email When will Avalon Rd be widen to help traffic flow. All we do is allow new subdivision and then we wait many years to improve the roads. I believe it's just about money and taxes. I have many more questions, but I will wait. link

    When will Avalon Rd be widen to help traffic flow. All we do is allow new subdivision and then we wait many years to improve the roads. I believe it's just about money and taxes. I have many more questions, but I will wait.

    Chris asked 13 days ago

    Thank you for your question. You can find more information about the Avalon Road transportation project here: Avalon Road (C.R. 545) Preliminary Design Study. If you have further questions about this project, please contact Brian Sanders at brian.sanders@ocfl.net or 407-836-8022. 

Page last updated: 10 Nov 2026, 04:40 PM